Project Name:**Environmental Energy Co., Ltd.

Project Introduction:

Project situation: An environmental protection energy company is a waste incineration power plant. It is equipped with a cooling circulating water system with a circulation of 6000m3/h. The supplementary water quality of the system is river water near the power plant, and the leachate is treated to produce water


The main problems of the project: bacteria and algae reproduction, slime, and water quality are complicated

Serial numberProjectSystem parameters
1
Circulating water volume (m3/h)

500

2Water retention m3300
3System equipment materialCarbon steel, copper, stainless steel
4Types of water treatment chemicalsCorrosion and scale inhibitor, bactericidal algicide, slime stripper

Project operation control results: the system has been operating stably throughout the year, the bacteria, algae and slime are basically controlled, and the terminal difference is stable at about 7℃

image.png

      Before taking over                                                                                                                                      After taking over